Design and Operation of the Multi-Intake 16 MW Box Canyon Run-of-River Hydroelectric Project

Design and Operation of the Multi-Intake 16 MW Box Canyon Run-of-River Hydroelectric Project

Author: Benoit Otis
Conference: HydroVision 2017
Date: June 27-30, 2017

ABSTRACT
The 16 MW Box Canyon Hydroelectric facility, located in southwest British Columbia, Canada was commissioned in early 2016. Knight Piésold Ltd. was retained by Box Canyon Hydro Corporation (a subsidiary of Elemental Energy) for the development phase, detail design and construction phases of the facility. The facility is comprised of three main water intakes, and six small tributary intakes. The water conveyance system includes approximately 7 km of pipeline connecting all intakes to a single 1 km (0.6 mile) long buried high-pressure steel penstock diverting generation flows of up to 3.96 m3/s. The facility operates under a gross head of 516.90 m.

Long-term (>20 years) synthetic stream flow datasets were developed for each creek, based on stream flow monitoring and a concurrent long-term regional discharge dataset. Detailed hydraulic analyses at varying discharge conditions for each creek was required to design a balanced water conveyance system, while also  determining the available gross head, net head and hydraulic transient conditions during the operations of the
facility.

Hydraulic analyses were completed using fluid dynamics principles and with KYPIPE analysis software. This allowed for comparison of the results and impacts of the theoretical considerations including friction losses and minor losses of the pipelines and penstock. Head losses and hydraulic transient conditions were detailed to define the operation ranges of the facility and to design and select the facility’s equipment. Penstock and pipelines materials were optimized in order to improve performance and lower the overall capital costs of the facility. Valves, instrumentation and generating equipment required careful selection for optimum operation at all design flow conditions, operation pressures and maximum efficiency. This paper and presentation will provide an overview of the key design challenges and innovative solutions conceived in the development of this multi-intake high-head run-of-river hydroelectric facility.

 

Download the full technical paper.

Download

Perspectivas recientes

Octubre 2025
2025 CCE Awards Showcase: Salton Sea Species Conservation Habitat Project
Septiembre 2025
Klamath River Renewal Project - Dam Breach Analysis Used for Designing the Final Breach of the Iron Gate Dam
Septiembre 2025
Klamath River Renewal Project - Optimization of the Iron Gate Dam Historic Diversion Tunnel Using CFD Analysis to Support Reservoir Drawdown
Septiembre 2025
Klamath River Renewal Project - Design of Dam Modification for Reservoir Drawdown, River Diversion and Dam Removal of the Copco No. 1 Dam
Septiembre 2025
Drawdown Modelling of Four Reservoirs on the Klamath River to Support Hydroelectric Facility Decommissioning
Septiembre 2025
Laying Groundwork for Future Mining: Infrastructure Support by Knight Piésold
Septiembre 2025
Lessons Learned in the Interpretation of SCPT on a Tailings Facility Using the CSSM Framework
Septiembre 2025
Challenges of Tailings Transport Pumping Systems in Negative Static Head Applications
Septiembre 2025
Hydraulic Evaluation of Tailings Transport Systems in Mountainous Terrain: Density Wave Analysis
Septiembre 2025
The Role of Rheology Tests in the Design and Operation of Long-Distance Slurry Transport Systems
Agosto 2025
The Evolution of Structural Domains from Scoping Study to Operations for the Meadowbank Mine – Amaruq Site
Agosto 2025
Safe Dams, Straight Talk: The Knight Piésold Difference
Julio 2025
Knight Piésold Zambia: Building a Future of Engineering Brilliance and Local Empowerment
Julio 2025
Water Engineering for Modern Mining: Bridging Mining with Sustainability
Junio 2025
The Essence of Material Compatibility in Advanced Barrier Systems of Existing TSFs
Junio 2025
Inverted Barriers in Tailings Storage Facilities: Lessons Learnt
Junio 2025
Prioritizing the Mitigation of Legacy Geomechanical Mine Hazards Using a Risk-Based Approach
Mayo 2025
Knight Piésold: Sustainable Projects in DRC Through Baseline Studies
Abril 2025
Advancements in Geotechnical Investigations for the Characterisation of Upstream Tailings Dams in SA
Noviembre 2024
Knight Piésold: Commitment to African Excellence