Design and Construction of the 45 MW Kokish River Hydroelectric Project in British Columbia, Canada

Design and Construction of the 45 MW Kokish River Hydroelectric Project in British Columbia, Canada

Author: Egbert J. Scherman, Sam R. Mottram
Conference: HydroVision International 2014
Date: July 22-25, 2014

This presentation will cover the design innovations and lessons learned from the detailed design and construction of the Kokish River Hydroelectric Project recently constructed in the northern part of Vancouver Island located in British Columbia, Canada. This hydroelectric facility is a private sector development by Kwagis Power, a limited partnership of Brookfield Renewable Energy Group and the ‘Namgis First Nation that was awarded an energy purchase agreement by BC Hydro in an open call for clean energy. The project will generate up to 45 MW of clean renewable energy that will be delivered to the British Columbia electrical grid, with an annual energy production capacity of roughly 140 GWh, enough electricity to power close to 13 000 homes.

The Kokish River Hydroelectric project is a run-of-river project with a maximum design generation flow of 25 m³/s and operating head of 238 m. Peter Kiewit Infrastructure Co. was awarded an EPC Contract for the design and construction of the project with Knight Piésold Ltd. appointed the Design Engineer for the project.

The terrain, climate and permitting constraints presented numerous challenges that were all overcome with some innovative design solutions and a close working relationship between the Owner, Contractor and Design Team. These included:

  • Dealing with migratory Salmon and Stealhead that are present throughout the diversion reach of the project, both during construction diversion and operation;
  •  A diversion weir with the world’s largest capacity Coanda screen capable of regulating water flow depth over the screen to ensure emerging salmon fry safe passage over the screens;
  • A 70 metre long vertical slotted fish ladder that allows continuous migration around the diversion weir for both resident trout populations and migrating salmon;
  • Hydraulic model testing of the entire diversion weir, intake structure and fish ladder;
  • A 1 474 m long buried HDPE low pressure penstock connected to a 7 703 m long
    buried, high pressure steel penstock, using soil restraint to eliminate expensive
    concrete anchor blocks;
  • A surface powerhouse housing four vertical axis six?jet Pelton type turbine-generator units capable of handling the long duration flow ramping rates associated with the project;
  • A Powerhouse tailrace channel fish fence, designed to prevent upstream migrating Salmon and Steelhead from entering the tailrace; and
  • A sophisticated in-stream flow measuring and flow ramping protocols.

 

Download the full technical paper.

Download

Recent Insights

October 2025
2025 CCE Awards Showcase: Salton Sea Species Conservation Habitat Project
September 2025
Klamath River Renewal Project - Dam Breach Analysis Used for Designing the Final Breach of the Iron Gate Dam
September 2025
Klamath River Renewal Project - Optimization of the Iron Gate Dam Historic Diversion Tunnel Using CFD Analysis to Support Reservoir Drawdown
September 2025
Klamath River Renewal Project - Design of Dam Modification for Reservoir Drawdown, River Diversion and Dam Removal of the Copco No. 1 Dam
September 2025
Drawdown Modelling of Four Reservoirs on the Klamath River to Support Hydroelectric Facility Decommissioning
September 2025
Laying Groundwork for Future Mining: Infrastructure Support by Knight Piésold
September 2025
Lessons Learned in the Interpretation of SCPT on a Tailings Facility Using the CSSM Framework
September 2025
Challenges of Tailings Transport Pumping Systems in Negative Static Head Applications
September 2025
Hydraulic Evaluation of Tailings Transport Systems in Mountainous Terrain: Density Wave Analysis
September 2025
The Role of Rheology Tests in the Design and Operation of Long-Distance Slurry Transport Systems
August 2025
The Evolution of Structural Domains from Scoping Study to Operations for the Meadowbank Mine – Amaruq Site
August 2025
Safe Dams, Straight Talk: The Knight Piésold Difference
July 2025
Knight Piésold Zambia: Building a Future of Engineering Brilliance and Local Empowerment
July 2025
Water Engineering for Modern Mining: Bridging Mining with Sustainability
June 2025
The Essence of Material Compatibility in Advanced Barrier Systems of Existing TSFs
June 2025
Inverted Barriers in Tailings Storage Facilities: Lessons Learnt
June 2025
Prioritizing the Mitigation of Legacy Geomechanical Mine Hazards Using a Risk-Based Approach
May 2025
Knight Piésold: Sustainable Projects in DRC Through Baseline Studies
April 2025
Advancements in Geotechnical Investigations for the Characterisation of Upstream Tailings Dams in SA
November 2024
Knight Piésold: Commitment to African Excellence