Design Considerations and Construction Strategies for the uMkhomazi Water Project Phase 1

Design Considerations and Construction Strategies for the uMkhomazi Water Project Phase 1

Authors: M. Nasiri1, G.J. Keyter1, U. Rehm2, T. Mac Kellar2
Conference: SANCOT Symposium 2026
Date: April 13-14, 2026

1 SRK Consulting, South Africa
2 Knight Piésold, South Africa

ABSTRACT

The uMkhomazi Water Project Phase 1 (uMWP-1) aims to augment water supply to the uMngeni Water Supply System (MWSS) in KwaZulu-Natal to address long-term regional water demand. A key component of the scheme is a 34 km waterway tunnel driven primarily by tunnel boring machines (TBMs), connecting the uMkhomazi intake to the Baynesfield outlet. The project presents several design and construction challenges, particularly due to the constraints of working within a relatively small 3.5 m internal diameter tunnel.

This paper outlines the main engineering strategies developed to manage these challenges, with preliminary design work completed to date, focused on practical solutions for tunnel logistics, including muck removal, segment transport, sequencing of construction activities, and the efficient use of equipment within the limited tunnel space. These aspects are essential in deriving workable construeition methods for these long, small-diameter TBM tunnels. The paper also summarises options for TBM removal at the Baynesfield outlet, which represents a major project milestone with implications for programme, cost, and interfaces with downstream infrastructure.

Overall, the study highlights the importance of coordinated planning, effective logistics, and careful sequencing during the preliminruy design phase to better manage construction risks and ensure long-term operability in complex tunnelling projects.

 

Download the full paper.

Download

Perspectivas recientes

Abril 2026
Considerations in the Design and Construction of Ventilation and Surge Shafts for the uMWP Phase 1 Water Transfer Tunnel
Abril 2026
The uMkhomazi Transfer Tunnel: Background, Geotechnical Conditions and Tunnel Design Considerations
Marzo 2026
Influencia de la interfaz en la estabilidad de un patio de lixiviación: un análisis de sensibilidad
Marzo 2026
Evaluación de alternativas para TSF mediante análisis de cuentas múltiples: selección de ubicación y método constructivo
Marzo 2026
El DAR como pilar de la gobernanza: GISTM: evaluación del impacto acumulativo del desviaciones en la gestión proactive de riesgos de depositos de jales. Estudio de caso.
Febrero 2026
A Method to Assess the Feasibility of Injection Leaching on Heap Leach Slopes
Enero 2026
Knight Piésold: Expanding Engineering Solutions Amid Africa's Mining Evolution
Noviembre 2025
Case Study: Assessing Construction-Induced Deformations in Tailings Storage Facility Embankments
Noviembre 2025
Geotechnical Characterization of Cyclone Underflow Tailings under High Confining Pressures
Octubre 2025
2025 CCE Awards Showcase: Salton Sea Species Conservation Habitat Project
Septiembre 2025
Klamath River Renewal Project - Dam Breach Analysis Used for Designing the Final Breach of the Iron Gate Dam
Septiembre 2025
Klamath River Renewal Project - Optimization of the Iron Gate Dam Historic Diversion Tunnel Using CFD Analysis to Support Reservoir Drawdown
Septiembre 2025
Klamath River Renewal Project - Design of Dam Modification for Reservoir Drawdown, River Diversion and Dam Removal of the Copco No. 1 Dam
Septiembre 2025
Drawdown Modelling of Four Reservoirs on the Klamath River to Support Hydroelectric Facility Decommissioning
Septiembre 2025
Klamath River Renewal Project
Septiembre 2025
Laying Groundwork for Future Mining: Infrastructure Support by Knight Piésold
Septiembre 2025
Lessons Learned in the Interpretation of SCPT on a Tailings Facility Using the CSSM Framework
Septiembre 2025
Challenges of Tailings Transport Pumping Systems in Negative Static Head Applications
Septiembre 2025
Hydraulic Evaluation of Tailings Transport Systems in Mountainous Terrain: Density Wave Analysis