Knight Piésold Southern Africa Appointed for Polihali Transfer Tunnel Design and Construction Supervision
Knight Piésold Southern Africa Appointed for Polihali Transfer Tunnel Design and Construction Supervision

Knight Piésold Southern Africa Appointed for Polihali Transfer Tunnel Design and Construction Supervision

May 9, 2018, Johannesburg, South AfricaThe Metsi a Senqu-Khubelu Consultants (MSKC) joint venture, consisting of Knight Piésold, Aurecon, Hatch, SMEC, and FM Associates, successfully concluded contract negotiations, with the Lesotho Highlands Development Authority (LDHA) in December 2017, for the multi-billion Maloti/Rand project called “Design and Construction Supervision of the Polihali Transfer Tunnel.”

This project forms part of Phase II of the Lesotho Highlands Water Project (LHWP), which is a bi-national water resources project initiative between the governments of Lesotho and South Africa.

A treaty signed between the two governments sets out the development structures that have been designed to include four phases, planned over a 30-year implementation period. The LHWP is expected to ultimately transfer approximately 70 m3/s of water to Gauteng in South Africa.

The project encompasses large-scale infrastructure to harness water resources from the highlands of Lesotho through the construction of a series of dams and tunnels for the mutual benefit of Lesotho and South Africa.

Water from the LHWP is transferred via the Katse Reservoir, through the Transfer Tunnel and Delivery Tunnel, to the Ash River Outfall between Clarens and Bethlehem in South Africa. Water flows from the Ash River into the Liebenbergsvlei, which joins the Wilge River near Frankfort before finally reaching the Vaal Dam in Gauteng. The associated bulk civil infrastructure was completed in Phase I of the LHWP, which was split into Phases 1A and 1B.

Phase II of the LHWP broadly comprises the design and construction of the following major components:

  • Polihali Dam, a concrete faced rockfill dam, located downstream of the confluence of the Senqu (Orange) and Khubelu Rivers in Lesotho
  • An approximately 38.5-km-long Polihali Transfer Tunnel to convey water from Polihali Reservoir to Katse Dam
  • All associated advance infrastructure, including access roads, bridges, construction camps, diversion tunnels at the Polihali dam site, healthcare facilities and programmes, and associated environmental and social studies and programmes.

The Polihali Transfer Tunnel will comprise an intake works at the new Polihali Reservoir, a 5-m-diameter and 38.5-km-long main water transfer tunnel, ventilation and dewatering shafts, and an outlet works at Katse that terminates in a Norwegian-type lake tap that is excavated by blasting inside the Katse Dam impoundment on the eastern flank of the existing reservoir.

The Transfer Tunnel appointment is MSKC’s second appointment on Phase II, with the MSKC also having been appointed for the “Design and Construction Supervision of the Polihali Diversion Tunnels” in September 2016. This was for the design and construction supervision of two diversion tunnels to facilitate river diversion during construction of the Polihali Dam, comprising a 7-m- and 9-m-diameter tunnel with length of 910 m and 960 m, respectively.

Recent News

April 14, 2023
Rubén Vargas Gives Insight on Tailings Dam Design and Management at ISEM's XXV International Mining Safety Seminar
April 12, 2023
Guillermo Barreda Presents at the Energy Transition Workshop by the British Embassy in Peru
February 15, 2023
Knight Piésold Canada Named Among British Columbia's Top Employers for Eleventh Year
February 13, 2023
Jeremy Haile Receives Canadian Consulting Engineer's Lifetime Achievement Award
November 24, 2022
Knight Piésold has Strong Presence at Tailings and Mine Waste 2022
November 07, 2022
Dr. Violeta Martin and Nick Rong Contribute to Dam Safety Technical Learning with the Canadian Dam Association Community
November 02, 2022
Knight Piésold Canada's Dr. Salina Yong and Daniel Yang Present a Case Study with KGHM on Managing Excessive Pit Wall Deformation at Slope Stability 2022
October 07, 2022
Knight Piésold Chile Receives "40-hour Seal" Certification
September 20, 2022
Kevin Davenport Presents Case Study on Observed Block Cave Subsidence Progression at Caving 2022
July 28, 2022
Knight Piésold Specialists Lend Expertise at HYDROVISION International 2022
July 18, 2022
Knight Piésold Argentina Certified as a Sustainable Company by the Municipality of Godoy Cruz
June 24, 2022
Michael Barrett Speaks at Mine Water Solutions 2022 on Hydrometric Monitoring and Effluent Discharge Mixing
June 20, 2022
Dr. Violeta Martin Presents Tailings Dam Breach Inundation Modelling at the ICOLD 2022 Congress
June 16, 2022
Dr. Colin Fyfe Joins Knight Piésold Canada as Specialist Hydrogeological Engineer
February 09, 2022
Knight Piésold Canada Celebrates 10 Years as a Top Employer in British Columbia
February 04, 2022
Knight Piésold Releases Its Engineer of Record Guidelines for Tailings Facilities
October 19, 2021
Knight Piésold Chile Pioneers the Application of BIM and AWP to Develop Mining Projects
October 07, 2021
Dr. Violeta Martin a Key Contributor to the CDA Technical Bulletin on Tailings Dam Breach Analysis
June 25, 2021
Knight Piésold Australia to Present Findings at Mine Waste and Tailings Conference in Brisbane
June 22, 2021
Knight Piésold Argentina Recognized for Environmental Commitment by the Municipality of Godoy Cruz