RTFE Lessons Learned from a TSF Buttressing Project

RTFE Lessons Learned from a TSF Buttressing Project

Authors: Eric Bates1
Conference: Tailings and Mine Waste 2026
Date: November 8–11, 2026

1 Knight Piésold, USA

ABSTRACT

The Responsible Tailings Facility Engineer (RTFE) role under the Global Industry Standard on Tailings Management (GISTM) assigns clear accountability for tailings facility integrity to a named individual within the operating organization. In practice, the delivery of risk-reduction measures is shaped by capital approval processes, mine sequencing constraints, material availability, and the organization’s perceptions of risk exposure and risk tolerance—factors that often fall outside the RTFE’s direct authority.

Drawing on the author’s personal experience as an RTFE at an operating mine site, this paper presents a case history of a Tailings Storage Facility (TSF) buttressing project in which a technically justified stabilization measure—fully investigated, funded, and planned—was delayed by interacting project dependencies and shifting perceptions of urgency. A key turning point occurred when the same technical information, presented in a decision-focused visual format, changed leadership's understanding of the consequences and accelerated action.

This paper is written in a systems-focused, no-blame spirit. The intent is not to critique the GISTM framework, the Engineer of Record (EOR), or mine site management, but to clarify how the RTFE role is put into practice, how potential roadblocks may arise in real-world situations, and how obstacles can be overcome. This case history illustrates how technically justified work can stall in real operating systems and what the author learned about communicating risk in a way that leads to action. Based on these lessons learned, practical approaches are suggested for use by RTFEs and other tailings practitioners who develop, review, and communicate recommendations to support the timely execution of risk-reduction work within mine site decision pathways, governance expectations, and day-to-day execution realities.

 

Download the full paper.

Download

Recent Insights

November 2026
A Framework for Interpreting Variable Penetration Rate CPTu Tests in Mine Tailings
November 2026
GeoStable Tailings Laboratory Mixture Trial
November 2026
Facing a Slithery Dragon: Systematics of the Petracola Ventrimaculata (Boulenger, 1900) Species Complex (Squamata: Gymnophthalmidae) with Description of Five New Species
October 2026
Improving Slope Deformation and Stability Predictions in Anisotropic Rock Masses: A Strain- and Confinement-Dependent Dilation Model for Ubiquitous Joints
October 2026
Integrated Approach to Rapidly Iterate Through LEA Stability Analyses for Design of Staged Construction Over Silty Clay Soils
October 2026
2026 CCE Award of Excellence: Site C Temporary Works
September 2026
Case Study: Paste Tailings Transport Optimization, Model Calibration and Concentration Sensitivity
September 2026
Multiple Account Analysis of Tailings Technologies to Define the Next TSF Stages
September 2026
Climate Change Considerations in Mine Water Management and Engineering Design for Reclamation Planning
August 2026
Beyond the Design Storm: From Compliance Metrics to Adaptive Operations for Consecutive Minor Events in Dams
August 2026
Knight Piésold: Engineering Namibia's Future
July 2026
Knight Piésold: Driving Integrated Water Management for Mining's Future
July 2026
Stochastic Hydrology Reveals the Controls of Forest Harvesting - Peakflow Causal Relations in Snow-Transient Environment
June 2026
From Liability to Asset: A Sustainable Approach for Mine Tailings Remediation in Peru
June 2026
Unsaturated Shear Strength Characteristics of Filtered Tailings through Modified Direct Simple Shear (MDSS) Apparatus
May 2026
Building Resilient Mines: Knight Piésold's Multidisciplinary Engineering Expertise
April 2026
Considerations in the Design and Construction of Ventilation and Surge Shafts for the uMWP Phase 1 Water Transfer Tunnel
April 2026
Design Considerations and Construction Strategies for the uMkhomazi Water Project Phase 1
April 2026
The uMkhomazi Transfer Tunnel: Background, Geotechnical Conditions and Tunnel Design Considerations