Wild Coast N2 Highway Project Taking Shape

Wild Coast N2 Highway Project Taking Shape

Publication: SAICE Civil Engineering
Issue: May 2024, Vol. 32, No. 4

The Wild Coast N2 Highway Project includes the construction of a 17.3 km greenfields portion of the new N2 highway. This portion of the new N2, known as Package 5, is located near Flagstaff in the Ingquza Hill Local Municipality in the Eastern Cape Province. It is being constructed in the form of a single carriageway road between the two new major bridges – Msikaba Bridge and Mtentu Bridge – which are both also currently under construction.

Knight Piésold Consulting is appointed by SANRAL for the engineering services for all project phases for Package 5, while WBHO-H&I Joint Venture is appointed as the main contractor. The project commenced in February 2023 and is progressing well.

Ongoing works include the exhumation and reburial of 188 existing graves along the new alignment and construction of 20 new houses to relocate affected families. Knight Piesold and WBHO-H&I JV work closely with the local chiefs and families to ensure all the needs of those affected are met. Also underway are the relocation of existing services, bulk earthworks, construction of several concrete culverts, and construction of the largest concrete structure along the Package 5 alignment, the 100 m long Kwadlambu River Bridge.

Package 5 will also cover the upgrading of existing divisional roads, rural tracks and the provision of new access roads (totaling 41 km), new underpass and overpass structures for pedestrian, cattle, and vehicle crossings as well as two new major interchanges.

The estimated construction cost of the project is R3.3 billion and the construction period is 54 months, with completion due in August 2027. The project will provide approximately 118 targeted enterprise subcontract packages for local subcontractors (CIDB gradings 1 to 6), and 300 work opportunities for the local community.

 

Read the article on Civil Engineering.

Download the full article.

Download

Recent Insights

November 2024
Design of a Co-disposal Facility for Thickened Tailings and Potentially Acid-generating Waste Rock
November 2024
Compaction Sensitivity in Tailings Stack Infiltration Modeling: Unsaturated Properties Uncertainty Analysis
November 2024
Volumes of Dam Material Mobilized by Erosion During Tailings Dam Failure Events
October 2024
Estudio de rotura de una presa de jales en la zona centro-norte de México
September 2024
Influence of Pre-Existing Mobilized Zones on B3 Cave Propagation and Initial Subsidence at the New Afton Mine
September 2024
Importance of Indigenous Community Engagement related to ARD/ML and Long-Term Water Quality
September 2024
Effective Assessment of ARD/ML Potential for Non-Mining Infrastructure Projects
August 2024
CESA Aon Engineering Excellence Awards 2024: Kikagati Hydropower Plant
July 2024
Interview: Mario Lazo Emparanza, Regional Manager, Knight Piésold Chile
July 2024
Visionary Leadership: Driving Engineering Excellence in Africa with Vishal Haripersad
June 2024
Concept Feasibility and Predicted Behavior of Mining a Rock Tower with Drill-and-Blast Undermining Using Dynamic Three-Dimensional Discontinuum Numerical Models
June 2024
Estimating Shear Stress within a Clay Foundation Using the Burgers-Creep Model
June 2024
Laboratory Study of Manganese Mining Overburden Mixed with Lime as a Paving Subbase Layer
May 2024
Knight Piésold: Ensuring African Excellence in the DRC
May 2024
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
April 2024
Risk Mitigation through Design Optimization Utilizing Seasonal Effects under Arctic Conditions at the Amaruq Mine
April 2024
Synthetic Rock Mass Modeling of Progressive Unravelling and Overall Slope Stability Using the Discrete Element Method
April 2024
Operational Slope Stability Risk Management for Large Open Pits at the Mount Milligan Mine – A Case Study
April 2024
Risk and Informed Approach to TSF Design and Operation