Benefits of Rotational, Thin Layer, Air Dried Tailing Deposition after 25-Years of Operation of the Juniper Tailing Storage Facility

Benefits of Rotational, Thin Layer, Air Dried Tailing Deposition after 25-Years of Operation of the Juniper Tailing Storage Facility

Author: Allen Gipson, Jason Taylor, Joseph Chilson, Brittany Hutchings
Conference: Tailings and Mine Waste 2018
Date: September 30-October 2, 2018

ABSTRACT
From inception in the late 1980s, the Juniper Tailings Storage Facility has been constructed in stages as a massive, compacted, rock fill, modified centerline embankment to retain fine grained predominately silt tailing. The initial cells were designed to contain 8 million tons. Three horizontal expansions and numerous staged raises have been made to the initial facility bringing the planned storage to 150 million tons at a height of 225 feet. Currently additional expansions are being considered. The initial stages of each basin were constructed as downstream embankments and the basins of each initial stage were lined with a 12-inch thick layer of low permeability soils overlain by a 12-inch thick drain layer containing a series of corrugated, slotted HDPE drain pipes. A drain/transition layer was included in the upstream face of the raises so that the fine-grained tailing did not migrate into the rock fill and any seepage was contained within the upstream side of the initial lined embankment where it was collected in the lined basin. Thus, no lining was needed above the initial embankment. This paper discusses the design, construction and operation of the facility including a summary of the benefits realized by the type of embankment constructed and the use of rotational, thin layered, air dried deposition. The features discussed could be considered for inclusion in other projects to provide safety and security, reduce costs and provide efficient operations.

 

Download the full technical paper.

Download

Perspectivas recientes

Octubre 2024
Estudio de rotura de una presa de jales en la zona centro-norte de México
Septiembre 2024
Influence of Pre-Existing Mobilized Zones on B3 Cave Propagation and Initial Subsidence at the New Afton Mine
Septiembre 2024
Importance of Indigenous Community Engagement related to ARD/ML and Long-Term Water Quality
Septiembre 2024
Effective Assessment of ARD/ML Potential for Non-Mining Infrastructure Projects
Agosto 2024
CESA Aon Engineering Excellence Awards 2024: Kikagati Hydropower Plant
Julio 2024
Interview: Mario Lazo Emparanza, Regional Manager, Knight Piésold Chile
Julio 2024
Visionary Leadership: Driving Engineering Excellence in Africa with Vishal Haripersad
Junio 2024
Concept Feasibility and Predicted Behavior of Mining a Rock Tower with Drill-and-Blast Undermining Using Dynamic Three-Dimensional Discontinuum Numerical Models
Junio 2024
Estimating Shear Stress within a Clay Foundation Using the Burgers-Creep Model
Junio 2024
Laboratory Study of Manganese Mining Overburden Mixed with Lime as a Paving Subbase Layer
Mayo 2024
Knight Piésold: Ensuring African Excellence in the DRC
Mayo 2024
Wild Coast N2 Highway Project Taking Shape
Mayo 2024
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
Abril 2024
Risk Mitigation through Design Optimization Utilizing Seasonal Effects under Arctic Conditions at the Amaruq Mine
Abril 2024
Synthetic Rock Mass Modeling of Progressive Unravelling and Overall Slope Stability Using the Discrete Element Method
Abril 2024
Operational Slope Stability Risk Management for Large Open Pits at the Mount Milligan Mine – A Case Study
Abril 2024
Risk and Informed Approach to TSF Design and Operation
Febrero 2024
Empoderamiento y Resiliencia
Enero 2024
Balancing Act: Water Usage Management Vital for a Sustainable Future
Enero 2024
A Difficult Balance Between Engineering, Environmental, Social and Economic Aspects