Design Considerations for the Capilano Energy Recovery Facility and Break Head Tank

Design Considerations for the Capilano Energy Recovery Facility and Break Head Tank

Author: Rob Adams
Conference: HydroVision 2017
Date: June 27-30, 2017

INTRODUCTION
Metro Vancouver (MV) is a public works organization that serves 18 municipalities (over 2 million people) in the greater Vancouver region of British Columbia, Canada. Amongst numerous other functions including waste collection and disposal, one of its primary tasks is to reliably provide clean, potable drinking water (over 1.1 million m3 per day average) to the residents of the cities served through a system of reservoirs, treatment facilities, pump stations and piping networks.

Most of Vancouver’s drinking water supply comes from watersheds in the mountains on the north side of the city (North Vancouver). Three main watersheds collect fresh water in three primary reservoirs. The reservoirs are protected and the water supply has historically been clean, with little need for elaborate treatment facilities. However, issues with turbidity, though not directly affecting potability, led in the 1990’s to the planning of a Filtration Plant to serve the Capilano and Seymour reservoirs (Seymour-Capilano Filtration Project, SCFP).

 

Download the full technical paper.

Download

Perspectivas recientes

Octubre 2024
Estudio de rotura de una presa de jales en la zona centro-norte de México
Septiembre 2024
Influence of Pre-Existing Mobilized Zones on B3 Cave Propagation and Initial Subsidence at the New Afton Mine
Septiembre 2024
Importance of Indigenous Community Engagement related to ARD/ML and Long-Term Water Quality
Septiembre 2024
Effective Assessment of ARD/ML Potential for Non-Mining Infrastructure Projects
Agosto 2024
CESA Aon Engineering Excellence Awards 2024: Kikagati Hydropower Plant
Julio 2024
Interview: Mario Lazo Emparanza, Regional Manager, Knight Piésold Chile
Julio 2024
Visionary Leadership: Driving Engineering Excellence in Africa with Vishal Haripersad
Junio 2024
Concept Feasibility and Predicted Behavior of Mining a Rock Tower with Drill-and-Blast Undermining Using Dynamic Three-Dimensional Discontinuum Numerical Models
Junio 2024
Estimating Shear Stress within a Clay Foundation Using the Burgers-Creep Model
Junio 2024
Laboratory Study of Manganese Mining Overburden Mixed with Lime as a Paving Subbase Layer
Mayo 2024
Knight Piésold: Ensuring African Excellence in the DRC
Mayo 2024
Wild Coast N2 Highway Project Taking Shape
Mayo 2024
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
Abril 2024
Risk Mitigation through Design Optimization Utilizing Seasonal Effects under Arctic Conditions at the Amaruq Mine
Abril 2024
Synthetic Rock Mass Modeling of Progressive Unravelling and Overall Slope Stability Using the Discrete Element Method
Abril 2024
Operational Slope Stability Risk Management for Large Open Pits at the Mount Milligan Mine – A Case Study
Abril 2024
Risk and Informed Approach to TSF Design and Operation
Febrero 2024
Empoderamiento y Resiliencia
Enero 2024
Balancing Act: Water Usage Management Vital for a Sustainable Future
Enero 2024
A Difficult Balance Between Engineering, Environmental, Social and Economic Aspects