Determining the Optimum Scheme Layout for the Sombwe Hydropower Project

Determining the Optimum Scheme Layout for the Sombwe Hydropower Project

Author: Edwin Lillie, Robert Greyling
Conference: Hydro 2018
Date: October 15-17, 2018

INTRODUCTION
Legislation in the DRC has recently changed to allow Independent Power Producers (IPP) to compete in the local power market. To this end, Kipay Investments appointed Knight Piésold and Ingerop Consulting Engineers to conduct a feasibility study for the proposed Sombwe Hydropower Project in late 2016. The project is located approximately 290 km north of Lubumbashi in the Katanga Province of the DRC, shown schematically in Figure 1. Two existing hydropower stations have been operating for many years upstream of the proposed Sombwe site. The 71 MW Mwadingusha hydropower plant at the Tshangalele Dam and the 36 MW Koni hydropower plant, which is located immediately downstream of Mwadingusha.

The catchment area at Sombwe is approximately 47 337 km2 and is characterised by two main sub-catchments. The Koni sub-catchment, with an area of approximately 12 877 km2 upstream of Koni Hydropower Station and the Sombwe dam incremental catchment downstream of Koni, having an area of approximately 34 450 km2. The Tshangalele Dam regulates the river flow from the Koni sub-catchment, whereas river flow in the Sombwe dam incremental catchment is unregulated. Based on available statistics of the existing upstream HPP schemes, and considering that the Sombwe site drains a significantly larger catchment, the applicable range for installed capacity is expected to lie between 80 MW and 160 MW.

It was initially envisaged that a dam with a final height of 70m to 100m would be required at Sombwe to provide sufficient head and yield for the power generation. However, as it is a Greenfield project, a number of different scheme layouts were investigated to select the most appropriate configuration for the feasibility study investigation.

To select the optimum scheme layout and component sizes, several parameters were considered before focusing the feasibility investigation on the selected option. The key output required from the options analyses study was
to determine;

  • Dam site and type,
  • Dam height,
  • Power plant capacity,
  • A single dam or a combination of dams in a cascade,
  • A surface or an underground powerhouse,
  • The initial estimated capital and operating cost estimates in sufficient detail to select a preferred option,
  • The long term average energy yield, and
  • The levelised cost of energy for all the plausible options.

There are too many parameters to optimise a scheme in a single analysis and a logical stepwise approach was undertaken to eliminate some parameters early on, but to retain those which may still influence the optimum scheme selection, until a decision could be made on the most economical solution. The objective was to select the most economical option for investigation at the feasibility level of detail with due consideration of technical, economic, environmental and social conditions.

 

Download the full technical paper.

Download

Perspectivas recientes

Noviembre 2024
Design of a Co-disposal Facility for Thickened Tailings and Potentially Acid-generating Waste Rock
Noviembre 2024
Compaction Sensitivity in Tailings Stack Infiltration Modeling: Unsaturated Properties Uncertainty Analysis
Noviembre 2024
Volumes of Dam Material Mobilized by Erosion During Tailings Dam Failure Events
Octubre 2024
Estudio de rotura de una presa de jales en la zona centro-norte de México
Septiembre 2024
Influence of Pre-Existing Mobilized Zones on B3 Cave Propagation and Initial Subsidence at the New Afton Mine
Septiembre 2024
Importance of Indigenous Community Engagement related to ARD/ML and Long-Term Water Quality
Septiembre 2024
Effective Assessment of ARD/ML Potential for Non-Mining Infrastructure Projects
Agosto 2024
CESA Aon Engineering Excellence Awards 2024: Kikagati Hydropower Plant
Julio 2024
Interview: Mario Lazo Emparanza, Regional Manager, Knight Piésold Chile
Julio 2024
Visionary Leadership: Driving Engineering Excellence in Africa with Vishal Haripersad
Junio 2024
Concept Feasibility and Predicted Behavior of Mining a Rock Tower with Drill-and-Blast Undermining Using Dynamic Three-Dimensional Discontinuum Numerical Models
Junio 2024
Estimating Shear Stress within a Clay Foundation Using the Burgers-Creep Model
Junio 2024
Laboratory Study of Manganese Mining Overburden Mixed with Lime as a Paving Subbase Layer
Mayo 2024
Knight Piésold: Ensuring African Excellence in the DRC
Mayo 2024
Wild Coast N2 Highway Project Taking Shape
Mayo 2024
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
Abril 2024
Risk Mitigation through Design Optimization Utilizing Seasonal Effects under Arctic Conditions at the Amaruq Mine
Abril 2024
Synthetic Rock Mass Modeling of Progressive Unravelling and Overall Slope Stability Using the Discrete Element Method
Abril 2024
Operational Slope Stability Risk Management for Large Open Pits at the Mount Milligan Mine – A Case Study
Abril 2024
Risk and Informed Approach to TSF Design and Operation