Grouting to reduce seepage at Neckartal Dam, Namibia

Grouting to reduce seepage at Neckartal Dam, Namibia

Authors: R. Greyling1, E. Lillie1, D. Mouton1, P. Segatto2
Conference: ICOLD Annual Meeting
Date: September 29-October 3, 2024

1 Knight Piésold, Pretoria, South Africa
2 Rostruct, Johannesburg, South Africa

ABSTRACT

Neckartal Dam is an 80m high RCC curved gravity dam in Namibia that spilt for the first time in January 2021. As the dam filled to full supply level (FSL), usual increases in seepage were observed, but all measured seepage rates were within stipulated acceptable limits for a large concrete dam.

Seepage from the dam is monitored at eight v-notch gauges in the dam galleries. During the course of the year, measured seepage at the gauges remained relatively constant or had even slightly decreased until May 2021, when seepage measurement from the upper left bank gallery v-notch gauge steadily increased to a rate that was no longer considered acceptable.

High seepage was observed predominately from a single drainage hole in the left bank, where the dam wall contacts a steep left bank foundation.

Volumetric changes occur within an RCC dam during the hydration and temperature dissipation cycle. Temperature rises due to cementitious hydration and will peak within the first couple of weeks following placement. However, once developed, it takes several years to dissipate to a steady state seasonal equilibrium temperature.

It is important for the safety of the dam that major seepage paths be sealed to avoid potential erosion of the foundation at the position of the open joint and/or flooding of the dam galleries, which may result in damage to electrical equipment for operating the hydromechanical equipment and the instrumentation for monitoring the behaviour of the dam.

In this paper, the authors describe the evaluations made and the approach followed to successfully reduce the seepage observed to an acceptable rate by undertaking sequenced precision drilling and grouting of a specific target area of the dam foundation post-construction. The grouting operation was particularly difficult, considering the high water pressures experienced from the full dam and several seepage paths through the foundation. The use of thick, stable cementitious grout, combined with systematic drilling, water pressure testing and grouting, was successful in reducing flow significantly.

 

Download the full paper.

Download

Perspectivas recientes

Noviembre 2024
Design of a Co-disposal Facility for Thickened Tailings and Potentially Acid-generating Waste Rock
Noviembre 2024
Compaction Sensitivity in Tailings Stack Infiltration Modeling: Unsaturated Properties Uncertainty Analysis
Noviembre 2024
Volumes of Dam Material Mobilized by Erosion During Tailings Dam Failure Events
Octubre 2024
Estudio de rotura de una presa de jales en la zona centro-norte de México
Septiembre 2024
Influence of Pre-Existing Mobilized Zones on B3 Cave Propagation and Initial Subsidence at the New Afton Mine
Septiembre 2024
Importance of Indigenous Community Engagement related to ARD/ML and Long-Term Water Quality
Septiembre 2024
Effective Assessment of ARD/ML Potential for Non-Mining Infrastructure Projects
Agosto 2024
CESA Aon Engineering Excellence Awards 2024: Kikagati Hydropower Plant
Julio 2024
Interview: Mario Lazo Emparanza, Regional Manager, Knight Piésold Chile
Julio 2024
A Diverse Approach in Geosynthetic Barrier Systems to Ensure Environmental Compliance of Existing TSFs
Julio 2024
Case History: Application Of Geosynthetics in A Tailings Storage Facility Rockfill Buttress Construction Project
Julio 2024
Visionary Leadership: Driving Engineering Excellence in Africa with Vishal Haripersad
Junio 2024
Concept Feasibility and Predicted Behavior of Mining a Rock Tower with Drill-and-Blast Undermining Using Dynamic Three-Dimensional Discontinuum Numerical Models
Junio 2024
Estimating Shear Stress within a Clay Foundation Using the Burgers-Creep Model
Junio 2024
Laboratory Study of Manganese Mining Overburden Mixed with Lime as a Paving Subbase Layer
Mayo 2024
Knight Piésold: Ensuring African Excellence in the DRC
Mayo 2024
Wild Coast N2 Highway Project Taking Shape
Mayo 2024
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
Abril 2024
Challenges in Ensuring Stability Whilst Providing Environmental Compliance for Existing TSFs