Operation of the Multi-Intake Box Canyon Run-of-River Hydroelectric Project to Meet Environmental Commitments

Operation of the Multi-Intake Box Canyon Run-of-River Hydroelectric Project to Meet Environmental Commitments

Author: Toby Perkins
Conference: HydroVision 2017
Date: June 27-30, 2017

ABSTRACT
The Box Canyon Hydroelectric Project is a 16 MW run-of-river facility located in the McNab Creek watershed on the north side of Howe Sound, British Columbia, Canada. The Project includes intake structures on three of the tributaries to McNab Creek (Box Canyon, Marty and Cascara Creeks) as well as six minor tributary diversions, all of which feed into a single high pressure penstock to direct water to the powerhouse. With this arrangement, it may have the most hydraulically complex design of any run-of-river hydroelectric project in North America, if not the world. The powerhouse includes a single, multi-jet Pelton turbine and water is returned to McNab Creek. The Project is connected to the BC Hydro transmission system via a 2.8 km long, 138 kV transmission line.

Knight Piésold Ltd. was retained by the owner, Box Canyon Hydro Corporation (a subsidiary of Elemental Energy) to assist with 1) concept development, environmental assessment and permitting, 2) detailed design, and 3) operational monitoring of the facility. The Project was commissioned in early 2016.

Under the Project’s Water License, the Project has maximum allowable diversion rates, minimum instream flow requirements (IFR) and maximum flow ramping rates. These requirements are different for each intake and in McNab Creek, due to differences in hydrology, river morphology and fish species distribution.

The IFR requirement at each intake is controlled by the intake design to ensure that IFR is released as priority before water is able to be diverted for power generation. Similarly, the maximum diversion rate is controlled by the intake design, which passively limits the maximum amount of water that is able to enter the penstock. However, flow ramping must be controlled by plant operation. This paper will provide an overview of the Project’s key Water License commitments and how the Project was designed and is operated to meet these commitments.

 

Download the full technical paper.

Download

Perspectivas recientes

Septiembre 2025
Laying Groundwork for Future Mining: Infrastructure Support by Knight Piésold
Septiembre 2025
Challenges of Tailings Transport Pumping Systems in Negative Static Head Applications
Septiembre 2025
Hydraulic Evaluation of Tailings Transport Systems in Mountainous Terrain: Density Wave Analysis
Septiembre 2025
The Role of Rheology Tests in the Design and Operation of Long-Distance Slurry Transport Systems
Agosto 2025
Safe Dams, Straight Talk: The Knight Piésold Difference
Julio 2025
Knight Piésold Zambia: Building a Future of Engineering Brilliance and Local Empowerment
Julio 2025
Water Engineering for Modern Mining: Bridging Mining with Sustainability
Junio 2025
The Essence of Material Compatibility in Advanced Barrier Systems of Existing TSFs
Junio 2025
Inverted Barriers in Tailings Storage Facilities: Lessons Learnt
Junio 2025
Prioritizing the Mitigation of Legacy Geomechanical Mine Hazards Using a Risk-Based Approach
Mayo 2025
Knight Piésold: Sustainable Projects in DRC Through Baseline Studies
Abril 2025
Advancements in Geotechnical Investigations for the Characterisation of Upstream Tailings Dams in SA
Noviembre 2024
Knight Piésold: Commitment to African Excellence
Noviembre 2024
Design of a Co-disposal Facility for Thickened Tailings and Potentially Acid-generating Waste Rock
Noviembre 2024
Compaction Sensitivity in Tailings Stack Infiltration Modeling: Unsaturated Properties Uncertainty Analysis
Noviembre 2024
Volumes of Dam Material Mobilized by Erosion During Tailings Dam Failure Events
Octubre 2024
Estudio de rotura de una presa de jales en la zona centro-norte de México
Septiembre 2024
Grouting to Reduce Seepage at Neckartal Dam, Namibia
Septiembre 2024
Influence of Pre-Existing Mobilized Zones on B3 Cave Propagation and Initial Subsidence at the New Afton Mine
Septiembre 2024
Importance of Indigenous Community Engagement related to ARD/ML and Long-Term Water Quality