Grouting to Reduce Seepage at Neckartal Dam, Namibia

Grouting to Reduce Seepage at Neckartal Dam, Namibia

Authors: R. Greyling1, E. Lillie1, D. Mouton1, P. Segatto2
Conference: ICOLD Annual Meeting
Date: September 29-October 3, 2024

1 Knight Piésold, Pretoria, South Africa
2 Rostruct, Johannesburg, South Africa

ABSTRACT

Neckartal Dam is an 80m high RCC curved gravity dam in Namibia that spilt for the first time in January 2021. As the dam filled to full supply level (FSL), usual increases in seepage were observed, but all measured seepage rates were within stipulated acceptable limits for a large concrete dam.

Seepage from the dam is monitored at eight v-notch gauges in the dam galleries. During the course of the year, measured seepage at the gauges remained relatively constant or had even slightly decreased until May 2021, when seepage measurement from the upper left bank gallery v-notch gauge steadily increased to a rate that was no longer considered acceptable.

High seepage was observed predominately from a single drainage hole in the left bank, where the dam wall contacts a steep left bank foundation.

Volumetric changes occur within an RCC dam during the hydration and temperature dissipation cycle. Temperature rises due to cementitious hydration and will peak within the first couple of weeks following placement. However, once developed, it takes several years to dissipate to a steady state seasonal equilibrium temperature.

It is important for the safety of the dam that major seepage paths be sealed to avoid potential erosion of the foundation at the position of the open joint and/or flooding of the dam galleries, which may result in damage to electrical equipment for operating the hydromechanical equipment and the instrumentation for monitoring the behaviour of the dam.

In this paper, the authors describe the evaluations made and the approach followed to successfully reduce the seepage observed to an acceptable rate by undertaking sequenced precision drilling and grouting of a specific target area of the dam foundation post-construction. The grouting operation was particularly difficult, considering the high water pressures experienced from the full dam and several seepage paths through the foundation. The use of thick, stable cementitious grout, combined with systematic drilling, water pressure testing and grouting, was successful in reducing flow significantly.

 

Download the full paper.

Download

Recent Insights

November 2026
Characterization of a Tailings Dam Foundation in Dolomitic Rock and Soft Soils and Proposed Treatment with Stone Columns Filled with Cement Grout
November 2026
Comparison of Remeshing and Material Point Method Approaches for Large-Strain Assessment of a Tailings Storage Facility Under Residual Undrained Strength Conditions
November 2026
Shear Strength Assessment of Run‑of‑Mine Waste Rock Used as Support Fill at the Aitik Mine Through Empirical Approaches
November 2026
RTFE Lessons Learned from a TSF Buttressing Project
November 2026
A Framework for Interpreting Variable Penetration Rate CPTu Tests in Mine Tailings
November 2026
GeoStable Tailings Laboratory Mixture Trial
November 2026
Facing a Slithery Dragon: Systematics of the Petracola Ventrimaculata (Boulenger, 1900) Species Complex (Squamata: Gymnophthalmidae) with Description of Five New Species
October 2026
Improving Slope Deformation and Stability Predictions in Anisotropic Rock Masses: A Strain- and Confinement-Dependent Dilation Model for Ubiquitous Joints
October 2026
Integrated Approach to Rapidly Iterate Through LEA Stability Analyses for Design of Staged Construction Over Silty Clay Soils
October 2026
2026 CCE Award of Excellence: Site C Temporary Works
September 2026
Case Study: Paste Tailings Transport Optimization, Model Calibration and Concentration Sensitivity
September 2026
Multiple Account Analysis of Tailings Technologies to Define the Next TSF Stages
September 2026
Climate Change Considerations in Mine Water Management and Engineering Design for Reclamation Planning
August 2026
Beyond the Design Storm: From Compliance Metrics to Adaptive Operations for Consecutive Minor Events in Dams
August 2026
Knight Piésold: Engineering Namibia's Future
July 2026
Knight Piésold: Driving Integrated Water Management for Mining's Future
July 2026
Stochastic Hydrology Reveals the Controls of Forest Harvesting - Peakflow Causal Relations in Snow-Transient Environment
June 2026
From Liability to Asset: A Sustainable Approach for Mine Tailings Remediation in Peru
June 2026
Unsaturated Shear Strength Characteristics of Filtered Tailings through Modified Direct Simple Shear (MDSS) Apparatus
May 2026
Building Resilient Mines: Knight Piésold's Multidisciplinary Engineering Expertise