Tailings Mobilization Estimates for Dam Breach Studies

Tailings Mobilization Estimates for Dam Breach Studies

Author: Daniel Fontaine, P.Eng., Violeta Martin, Ph.D., P.Eng.
Conference: Tailings and Mine Waste 2015
Date: October 25-28, 2015

Quantitative assessment of potential consequences caused by a flood from a dam breach of a tailings facility requires an estimate of the volume of water and tailings released during the breach. A methodology for estimating the volume of tailings mobilized by the free water stored in the pond and the resulting initial flood wave following a dam breach is presented.

Tailings mobilization can be estimated as a function of the stored water volume and the physical characteristics of the tailings deposit. The result is an estimate of the total outflow consisting of volumes of free water, and tailings and interstitial water that could be potentially mobilized. This approach indicates that a larger operating pond would mobilize more tailings than a smaller pond.

Similarly, a tailings deposit that is more consolidated or only partially saturated would result in a smaller volume of tailings being released in a breach. These are the primary attributes of stored tailings affecting the potential consequences of a breach. An understanding of these attributes allows the practitioner to use the results of the analysis as a decision making tool for decreasing the consequences of failure.

 

Download the full technical paper.

Download

Recent Insights

July 2024
Visionary Leadership: Driving Engineering Excellence in Africa with Vishal Haripersad
June 2024
Concept Feasibility and Predicted Behavior of Mining a Rock Tower with Drill-and-Blast Undermining Using Dynamic Three-Dimensional Discontinuum Numerical Models
June 2024
Estimating Shear Stress within a Clay Foundation Using the Burgers-Creep Model
June 2024
Laboratory Study of Manganese Mining Overburden Mixed with Lime as a Paving Subbase Layer
May 2024
Knight Piésold: Ensuring African Excellence in the DRC
May 2024
Wild Coast N2 Highway Project Taking Shape
April 2024
Risk Mitigation through Design Optimization Utilizing Seasonal Effects under Arctic Conditions at the Amaruq Mine
April 2024
Synthetic Rock Mass Modeling of Progressive Unravelling and Overall Slope Stability Using the Discrete Element Method
April 2024
Operational Slope Stability Risk Management for Large Open Pits at the Mount Milligan Mine – A Case Study
April 2024
Risk and Informed Approach to TSF Design and Operation
February 2024
Empowerment and Resilience
January 2024
Balancing Act: Water Usage Management Vital for a Sustainable Future
January 2024
A Difficult Balance Between Engineering, Environmental, Social and Economic Aspects
November 2023
Knight Piésold Commences with the ESIA for Haib Copper
November 2023
Insights from the Compilation and Critical Assessment of Breach and Runout Characteristics from Historical Tailings Dam Failures: Implications for Numerical Modelling
November 2023
Earthquake-induced Deformation Analysis of a TSF Undergoing Tailings Reprocessing
November 2023
Case Study: Approach to Determining the Risk Mitigation Priority of a Historic TSF in North America
October 2023
Data Management and Insights for Effective Tailings Storage Facility Management
October 2023
The Role of Sensitivity Analysis in Selecting Dam Breach Parameters
October 2023
Influence of Increased Confining Stress on Undrained Behavior of Tailings: A Case History at the Candelaria Mine