A Brief History of the RCC at Neckartal Dam

A Brief History of the RCC at Neckartal Dam

Author: Edwin Lillie, Elvin Pesch, Louis Barnard
Conference: SANCOLD Annual Conference and AGM 2018
Date: November 7-9, 2018

ABSTRACT
The construction of Neckartal Dam started in September 2013. The full-scale trial section was done in August 2015 and the first RCC was placed on the dam foundation in October 2015. The RCC placement was completed 32 months later in May 2018. This paper gives a brief history of the RCC through the various project phases. Two mixes were used, a 20/38 high cementitious mix for an impermeable zone (Zone 1) in the upstream face of the dam and two 10/38 low cementitious mixes for the main body of the dam (Zone 2). The Contractor produced a total of 3.12 million tons of aggregate for the project over 33 months at an average of 94 800 tons per month. The overall crushing plant efficiency over the 33 months of production was 33%. The Contractor produced a total of 836 000m3 of RCC for the project over 32 months at an average rate of 26 127m3 per month. The overall plant efficiency over the 32 months was 17%. Over the whole RCC placement period, there were interruptions for many reasons, some within the Contractor’s control such as plant breakdowns, insufficient sand, cement and/or fly ash, waiting for shutters to be moved, preparing RCC surfaces, sequencing of the intake tower construction etc. There were also some delays beyond the Contractor’s control such as strikes, break downs and late payments. The RCC cube tests indicated that the set RCC easily achieved the strength requirements of the project specification of 20MPa at 365 days for Zone 1 and 10MPa at 365 days for Zone 2.

 

Download the full technical paper.

Download

Recent Insights

May 2023
Is the Implementation of Dry Stacking for Tailings Storage Increasing? A Southern African Perspective
February 2023
Canadian Consulting Engineer's Lifetime Achievement Awards: Jeremy Haile
February 2023
Geotechnical Characterization of Collapsible Salty Sands Subjected to Monotonic and Cyclic Loadings – A Case Study for Areas with High Seismicity
November 2022
Application of the 3D Limit Equilibrium Method in Tailings Dam Breach Analysis
November 2022
Evaluation of Tailings Behaviour for Dam Breach Assessments
November 2022
Tailings Improvement by Stress-Densification from Waste Rock Capping
November 2022
Transforming Tailings Management Systems toward Alignment with the GISTM: A Case History
October 2022
Managing Excessive Pit Wall Deformation of Weak Rock Mass
October 2022
State-of-the-art Method for Estimating Long-term Hydroclimatic Conditions for Tailing Dam Water Management and Dam Safety Planning
August 2022
Observed Subsidence Progression at New Afton Mine in Response to Lift 1 Mining
June 2022
Hydrometric Monitoring and Effluent Discharge Mixing in Challenging Natural Conditions
May 2022
Inundation Modelling of Non-Newtonian Tailings Dam Breach Outflows
May 2022
Video: Tailings Management Compliancy Picks Up Momentum
May 2022
A Catch up with...Richard Elmer
February 2022
Engineer of Record Services for Tailings Facilities
November 2021
Knight Piésold's Projects Commended at Prestigious Awards
November 2021
Advances in Ensuring Tailings Dam Safety
November 2021
Gearing Up for Growth in Zambia
October 2021
Climate Change Effects on Rainfall Extremes and Implications for Highway Drainage Structures
October 2021
Knight Piésold, aliado de la minería sustentable