Design and Construction of the 45 MW Kokish River Hydroelectric Project in British Columbia, Canada

Design and Construction of the 45 MW Kokish River Hydroelectric Project in British Columbia, Canada

Author: Egbert J. Scherman, Sam R. Mottram
Conference: HydroVision International 2014
Date: July 22-25, 2014

This presentation will cover the design innovations and lessons learned from the detailed design and construction of the Kokish River Hydroelectric Project recently constructed in the northern part of Vancouver Island located in British Columbia, Canada. This hydroelectric facility is a private sector development by Kwagis Power, a limited partnership of Brookfield Renewable Energy Group and the ‘Namgis First Nation that was awarded an energy purchase agreement by BC Hydro in an open call for clean energy. The project will generate up to 45 MW of clean renewable energy that will be delivered to the British Columbia electrical grid, with an annual energy production capacity of roughly 140 GWh, enough electricity to power close to 13 000 homes.

The Kokish River Hydroelectric project is a run-of-river project with a maximum design generation flow of 25 m³/s and operating head of 238 m. Peter Kiewit Infrastructure Co. was awarded an EPC Contract for the design and construction of the project with Knight Piésold Ltd. appointed the Design Engineer for the project.

The terrain, climate and permitting constraints presented numerous challenges that were all overcome with some innovative design solutions and a close working relationship between the Owner, Contractor and Design Team. These included:

  • Dealing with migratory Salmon and Stealhead that are present throughout the diversion reach of the project, both during construction diversion and operation;
  •  A diversion weir with the world’s largest capacity Coanda screen capable of regulating water flow depth over the screen to ensure emerging salmon fry safe passage over the screens;
  • A 70 metre long vertical slotted fish ladder that allows continuous migration around the diversion weir for both resident trout populations and migrating salmon;
  • Hydraulic model testing of the entire diversion weir, intake structure and fish ladder;
  • A 1 474 m long buried HDPE low pressure penstock connected to a 7 703 m long
    buried, high pressure steel penstock, using soil restraint to eliminate expensive
    concrete anchor blocks;
  • A surface powerhouse housing four vertical axis six?jet Pelton type turbine-generator units capable of handling the long duration flow ramping rates associated with the project;
  • A Powerhouse tailrace channel fish fence, designed to prevent upstream migrating Salmon and Steelhead from entering the tailrace; and
  • A sophisticated in-stream flow measuring and flow ramping protocols.

 

Download the full technical paper.

Download

Recent Insights

May 2023
Is the Implementation of Dry Stacking for Tailings Storage Increasing? A Southern African Perspective
February 2023
Canadian Consulting Engineer's Lifetime Achievement Awards: Jeremy Haile
February 2023
Geotechnical Characterization of Collapsible Salty Sands Subjected to Monotonic and Cyclic Loadings – A Case Study for Areas with High Seismicity
November 2022
Application of the 3D Limit Equilibrium Method in Tailings Dam Breach Analysis
November 2022
Evaluation of Tailings Behaviour for Dam Breach Assessments
November 2022
Tailings Improvement by Stress-Densification from Waste Rock Capping
November 2022
Transforming Tailings Management Systems toward Alignment with the GISTM: A Case History
October 2022
Managing Excessive Pit Wall Deformation of Weak Rock Mass
October 2022
State-of-the-art Method for Estimating Long-term Hydroclimatic Conditions for Tailing Dam Water Management and Dam Safety Planning
August 2022
Observed Subsidence Progression at New Afton Mine in Response to Lift 1 Mining
June 2022
Hydrometric Monitoring and Effluent Discharge Mixing in Challenging Natural Conditions
May 2022
Inundation Modelling of Non-Newtonian Tailings Dam Breach Outflows
May 2022
Video: Tailings Management Compliancy Picks Up Momentum
May 2022
A Catch up with...Richard Elmer
February 2022
Engineer of Record Services for Tailings Facilities
November 2021
Knight Piésold's Projects Commended at Prestigious Awards
November 2021
Advances in Ensuring Tailings Dam Safety
November 2021
Gearing Up for Growth in Zambia
October 2021
Climate Change Effects on Rainfall Extremes and Implications for Highway Drainage Structures
October 2021
Knight Piésold, aliado de la minería sustentable