Heap Leach Pads - The Importance of Proper Testing, Interpretation, and Analysis of Soil Liner Geomembrane Interfaces

Heap Leach Pads - The Importance of Proper Testing, Interpretation, and Analysis of Soil Liner Geomembrane Interfaces

Author: Guillermo Barreda, Luis Chahua
Conference: Heap Leach Solutions 2014
Date: November 10-13, 2014

The design of heap leach pads involves a variety of components. One of the main components for these structures is the leach pad liner system, where a low-permeability soil is normally used in combination with a geomembrane to reduce seepage losses. Although this combination of materials has been shown to effectively reduce rates of infiltration, the soil liner-geomembrane interface presents a challenge to designers since it incorporates a “weak layer” into the system, which has negative effects on the physical stability of the structure.

Usually, the effects produced by the soil liner-geomembrane interface govern the stability of the heap leach pads; therefore, it is critical to characterize its behavior by (a) proper sampling and testing— for example, taking into account the design loads that will be imposed by the heap; (b) proper interpretation—for example, taking into account the nonlinear behavior of the interface; and (c) proper application of the results to the analysis—for example, assessing the use of post-peak and large displacement values. Lastly, verifications must be carried out during construction to ensure that the assumptions made during the design are implemented on site.

Although there are papers that discuss these issues individually, the intention of this paper is to present from the designer perspective the key variables to consider at each stage (sampling, testing, interpretation, analysis, and verification during construction). The approach will take into consideration an interface-testing database with more than 10 years of test results, and the experience gained in the interpretation and analysis of these results for heap leach pad projects developed in Peru.

Oversimplification of decisions related to testing, interpretation, and analysis of the soil liner-geomembrane interface can lead to potential economic, environmental, and safety impacts to the project, as well as an increase of the risk levels of the structure. Therefore, the implications of identification and discussion of the variables at each of these stages are important not only to designers, but also to other parties such as clients, manufacturers, and construction companies.

 

Download the full technical paper.

Download

Recent Insights

October 2025
2025 CCE Awards Showcase: Salton Sea Species Conservation Habitat Project
September 2025
Klamath River Renewal Project - Dam Breach Analysis Used for Designing the Final Breach of the Iron Gate Dam
September 2025
Klamath River Renewal Project - Optimization of the Iron Gate Dam Historic Diversion Tunnel Using CFD Analysis to Support Reservoir Drawdown
September 2025
Klamath River Renewal Project - Design of Dam Modification for Reservoir Drawdown, River Diversion and Dam Removal of the Copco No. 1 Dam
September 2025
Drawdown Modelling of Four Reservoirs on the Klamath River to Support Hydroelectric Facility Decommissioning
September 2025
Laying Groundwork for Future Mining: Infrastructure Support by Knight Piésold
September 2025
Lessons Learned in the Interpretation of SCPT on a Tailings Facility Using the CSSM Framework
September 2025
Challenges of Tailings Transport Pumping Systems in Negative Static Head Applications
September 2025
Hydraulic Evaluation of Tailings Transport Systems in Mountainous Terrain: Density Wave Analysis
September 2025
The Role of Rheology Tests in the Design and Operation of Long-Distance Slurry Transport Systems
August 2025
The Evolution of Structural Domains from Scoping Study to Operations for the Meadowbank Mine – Amaruq Site
August 2025
Safe Dams, Straight Talk: The Knight Piésold Difference
July 2025
Knight Piésold Zambia: Building a Future of Engineering Brilliance and Local Empowerment
July 2025
Water Engineering for Modern Mining: Bridging Mining with Sustainability
June 2025
The Essence of Material Compatibility in Advanced Barrier Systems of Existing TSFs
June 2025
Inverted Barriers in Tailings Storage Facilities: Lessons Learnt
June 2025
Prioritizing the Mitigation of Legacy Geomechanical Mine Hazards Using a Risk-Based Approach
May 2025
Knight Piésold: Sustainable Projects in DRC Through Baseline Studies
April 2025
Advancements in Geotechnical Investigations for the Characterisation of Upstream Tailings Dams in SA
November 2024
Knight Piésold: Commitment to African Excellence