Investigation of Sediment Transport Through a Run-of-River Hydroelectric Project

Investigation of Sediment Transport Through a Run-of-River Hydroelectric Project

Author: Violeta Martin, Michael Pullinger, Alana Shewan, Nathan Smith
Conference: HydroVision International 2014
Date: July 22-25, 2014

A 25 MW run-of-river hydroelectric project is proposed in coastal British Columbia, Canada. Baseline studies identified that the bedload sediment transport rate in the project area is relatively low, and consequently, interruption of bed material replenishment in the reaches downstream of the intake represents an environmental concern.

A prerequisite for the successful design of the proposed project includes passing of the spawning size gravel through the intake facility during the period of headpond sediment infilling. A sluice gate has been incorporated in the intake structure to enable the sluicing of sediment. Numerical modelling was undertaken to aid with the intake design and to determine the sediment transport efficiency through the headpond. Hydrodynamic modelling techniques (1D, 2D and CFD) were combined to assess the proposed design and provide an overview of water depths, velocities and bed shear stresses along with the potential for gravel mobility through the headpond reach both before and after the construction of the intake.

 

Download the full technical paper.

Download

Recent Insights

November 2021
Knight Piésold's Projects Commended at Prestigious Awards
November 2021
Engineer of Record Services for Tailings Facilities
November 2021
Gearing Up for Growth in Zambia
October 2021
Knight Piésold, aliado de la minería sustentable
September 2021
Knight Piésold Chile enfoque personalizado e integral de trabajo al estilo boutique
September 2021
Company Uses Innovative Ideas in Municipal Project
August 2021
South Africa Must Focus on STEM Skills to Enable Development
July 2021
Business Success Stories: Knight Piésold
July 2021
Holistic Approach to Mine and Industrial Water Management
July 2021
Selection of Undrained Shear Strength Parameters of Residual Soils and their Application in Stability Analysis
June 2021
Knight Piésold Focused on Africa's Infrastructure Development
June 2021
Century-old Knight Piésold Remains Committed to Clients and Communities in Phalaborwa
May 2021
Very Few Consulting Firms Reach 100 Years – Knight Piésold Celebrates with Optimism
April 2021
Knight Piésold Celebrates 100 Years of Excellence in Africa
April 2021
Video: Knight Piésold Celebrates 100 Years of Engineering Excellence
April 2021
Opportunities Abound to Support Africa's Resilient Growth - Knight Pièsold
April 2021
Firm Expands Service Offering
March 2021
Celebrating 100 Years of Engineering Excellence
February 2021
Improved Tailings Disposal Could Reduce Water Use
January 2021
Your Community, Your Neighbour