Mount Polley Tailings Dam Failure - More Lessons to Learn

Mount Polley Tailings Dam Failure - More Lessons to Learn

Author: Ken J. Brouwer, Greg L. Smyth 
Conference: CIM 2017 Convention
Date: April 30-May 3, 2017

ABSTRACT
The Mount Polley Tailings Facility was first constructed in 1996 at a time when three new mines were under development in BC, Canada (Mount Polley, Huckleberry and Kemess South). The design, review and regulatory oversight of these three projects were influenced by tailings facility failures that had occurred at that time (Merriespruit, South Africa (1994), Omai, Guyana (1995)). Qualified geotechnical engineers developed designs, Independent  ngineering Reviews were conducted, and enforcement of mining regulations occurred with strong participation by the Provincial Government. The concurrent development of these mines allowed for lessons learned from one project to be applied to the others. For example, foundation instability in glaciolacustrine soils encountered during construction of the starter dam at the Kemess Tailings Facility resulted in review of similar glaciolacustrine soils at the Mount Polley Tailings Facility, and the early embankment designs incorporated suitably flat and/or buttressed slopes to accommodate the potentially weak foundation conditions. The Mount Polley dam failure occurred after the facility design was modified by incorporating steeper overall slopes for the higher embankments. Recent regulatory changes in BC mandate Independent Review Boards along with increased inspections by Regulators for tailings facilities. This will result in more conservative designs with increased oversight during all phases of mine operations, in order to foster a safer mining industry.

 

Download the full technical paper.

Download

Recent Insights

July 2024
Visionary Leadership: Driving Engineering Excellence in Africa with Vishal Haripersad
June 2024
Concept Feasibility and Predicted Behavior of Mining a Rock Tower with Drill-and-Blast Undermining Using Dynamic Three-Dimensional Discontinuum Numerical Models
June 2024
Estimating Shear Stress within a Clay Foundation Using the Burgers-Creep Model
June 2024
Laboratory Study of Manganese Mining Overburden Mixed with Lime as a Paving Subbase Layer
May 2024
Knight Piésold: Ensuring African Excellence in the DRC
May 2024
Wild Coast N2 Highway Project Taking Shape
April 2024
Risk Mitigation through Design Optimization Utilizing Seasonal Effects under Arctic Conditions at the Amaruq Mine
April 2024
Synthetic Rock Mass Modeling of Progressive Unravelling and Overall Slope Stability Using the Discrete Element Method
April 2024
Operational Slope Stability Risk Management for Large Open Pits at the Mount Milligan Mine – A Case Study
April 2024
Risk and Informed Approach to TSF Design and Operation
February 2024
Empowerment and Resilience
January 2024
Balancing Act: Water Usage Management Vital for a Sustainable Future
January 2024
A Difficult Balance Between Engineering, Environmental, Social and Economic Aspects
November 2023
Knight Piésold Commences with the ESIA for Haib Copper
November 2023
Insights from the Compilation and Critical Assessment of Breach and Runout Characteristics from Historical Tailings Dam Failures: Implications for Numerical Modelling
November 2023
Earthquake-induced Deformation Analysis of a TSF Undergoing Tailings Reprocessing
November 2023
Case Study: Approach to Determining the Risk Mitigation Priority of a Historic TSF in North America
October 2023
Data Management and Insights for Effective Tailings Storage Facility Management
October 2023
The Role of Sensitivity Analysis in Selecting Dam Breach Parameters
October 2023
Influence of Increased Confining Stress on Undrained Behavior of Tailings: A Case History at the Candelaria Mine