Selecting the Optimum Hydropower Scheme Capacity

Selecting the Optimum Hydropower Scheme Capacity

Author: C Zhang, E Lillie
Conference: SANCOLD 2019 Annual Conference
Date: November 6-8, 2019

ABSTRACT
To select the optimum dam height and plant capacity, a high-level design should be prepared for a range of the dam heights and plant sizes at a potential site. The capital and operating costs should be determined for the proposed scheme for the expected life of the project. Then the long-term energy production should be calculated using a hydrological model. The marginal cost and the marginal revenue should be calculated for the range of scheme sizes. The optimum scheme size is when the marginal cost exceeds the marginal revenue. A sensitivity analyses should be done on all the main input parameters. This paper deals with selecting the optimum scheme capacity for a site using the established economic optimisation method of total revenue – total cost approach and marginal analysis, which mitigates the bias in selecting the scheme capacity.

BACKGROUND
Hydropower electricity generation in the world has reached a new high of approximately 4200 terawatt hours (TWh) in 2018, of this 4200TWh, only 138 TWh, 3.3 %, is contributed from Africa. New hydropower capacity of 21.8 Gigawatts (GW) was put into operation in 2018, in which Africa contributed 1 GW from 7 different countries. (IHA, 2019). This bringing Africa’s total installed capacity to 36.3GW, 2.8 % of the world’s total installed capacity. Figure 1 shows the 2918 distribution of hydropower development across the different regions of the world.

With 640 million Africans having no access to electricity according to the African Development Bank Group (ADBG)(African Development Bank Group, 2019) there is a great need for energy generation in Africa. Many sources state that Africa has the largest percentage of untapped hydropower potential with only 11 % utilised. Figure 2 shows the distribution of hydropower development across the Africa.

It should be noted that a large proportion of the installed hydropower capacity in South Africa is pumped storage to balance the daily power fluctuation in the South Africa grid.

With Africa having the largest percent of untapped hydropower potential, hydropower projects are an important driver for new dam construction projects in Africa. With there being a shortage of public finance for power development in Africa there is a huge emphasis on needing to attract private sector financing, this comes with a certain difficulty in which one must mitigate the risks that are perceived by the investors. It is important for developers to optimise their investments and the African challenges that one must contend with deter private capital (Kalitsi EAK, 2003). Thus, it is important to optimize the capacity of new hydropower schemes when such opportunity comes.

In selecting the optimum capacity for a new hydropower plant, it is important to consider a range of dam heights and plant sizes for a site. The annual average energy production for a site is dependent on both factors as well as other factors such as the water resource available and electricity tariff structures. This paper will outline the method used to select the optimal hydropower scheme capacity for a potential site. A theoretical case study is presented to demonstrate this method.

 

Download the full technical paper.

Download

Recent Insights

May 2023
Is the Implementation of Dry Stacking for Tailings Storage Increasing? A Southern African Perspective
February 2023
Canadian Consulting Engineer's Lifetime Achievement Awards: Jeremy Haile
February 2023
Geotechnical Characterization of Collapsible Salty Sands Subjected to Monotonic and Cyclic Loadings – A Case Study for Areas with High Seismicity
November 2022
Application of the 3D Limit Equilibrium Method in Tailings Dam Breach Analysis
November 2022
Evaluation of Tailings Behaviour for Dam Breach Assessments
November 2022
Tailings Improvement by Stress-Densification from Waste Rock Capping
November 2022
Transforming Tailings Management Systems toward Alignment with the GISTM: A Case History
October 2022
Managing Excessive Pit Wall Deformation of Weak Rock Mass
October 2022
State-of-the-art Method for Estimating Long-term Hydroclimatic Conditions for Tailing Dam Water Management and Dam Safety Planning
August 2022
Observed Subsidence Progression at New Afton Mine in Response to Lift 1 Mining
June 2022
Hydrometric Monitoring and Effluent Discharge Mixing in Challenging Natural Conditions
May 2022
Inundation Modelling of Non-Newtonian Tailings Dam Breach Outflows
May 2022
Video: Tailings Management Compliancy Picks Up Momentum
May 2022
A Catch up with...Richard Elmer
February 2022
Engineer of Record Services for Tailings Facilities
November 2021
Knight Piésold's Projects Commended at Prestigious Awards
November 2021
Advances in Ensuring Tailings Dam Safety
November 2021
Gearing Up for Growth in Zambia
October 2021
Climate Change Effects on Rainfall Extremes and Implications for Highway Drainage Structures
October 2021
Knight Piésold, aliado de la minería sustentable