Steel Reticulation Design Excels

Steel Reticulation Design Excels

Publication: IMIESA
Issue: November/December 2018

Serving the growing needs of the City of eThekwini’s industrial and residential sectors is an expanding network of steel pipelines that traverse the hilly terrain common in this region. The challenging topography calls for innovative design and construction methodologies, which had a direct bearing on the pipeline reticulation system adopted.

For the Western Aqueduct Phase 2 component from Inchanga to Hillcrest, the steel pipes selected were manufactured and supplied by Hall Longmore, a market leader in South Africa and internationally since 1924. Both contracts for Phase 2 were completed in 2015.

Contract WS6190 comprised some 7 km of DN 1 600 steel pipe from Inchanga Station to Alverstone Nek Reservoir, with a short section of DN 1 400 steel pipe at Alverstone Nek Reservoir. The maximum static pressure in this stage is 29 bar, requiring 13.5 mm thick X65-grade steel pipe.

The final section (Contract WS6191) comprised approximately 7.5 km of DN 1 400 steel pipe from Alverstone Nek Reservoir to the Ashley Drive Break Pressure Tank (BPT). The maximum static pressure in this case is 25 bar, requiring 12 mm thick X65-grade steel pipe at high-pressure sections. The Ashley Drive BPT was designed for a through-flow capacity of 400 M?/day.

The Western Aqueduct was conceived as a large-diameter, thin-walled, continuously welded steel pipe. The steel pipe was selected to be both economical and functional. In low-pressure areas, this typically meant using the thinnest available X42-grade steel pipe, subject to typical slenderness limits not being exceeded. The thinnest wall was 10 mm on the DN 1 400 pipeline and 12 mm on the DN 1 600 pipeline, giving respective slenderness ratios of 140 and 133.

When pressure increases necessitated higher-strength pipe, the grade of steel pipe was changed in the first instance before increasing the wall thickness, as this was found to be a more economical solution – e.g. 10 mm wall thickness X42-grade pipe was upgraded to 10 mm thick X52-grade pipe, rather than, say, 12 mm thick X42-grade pipe. The highest grade of pipe specified was a 13.5 mm thick X65-grade steel pipe with a minimum yield strength of 448 MPa.

The pipeline was designed to be continuously welded, which resulted in the pipe wall stresses having to be calculated at every point of intersection. Because concrete thrust blocks were not a practical means of restraining longitudinal forces in such a large-diameter pressurised pipeline, these forces were taken up in the pipe itself.

 

Download the full technical paper.

Download

Recent Insights

September 2025
Laying Groundwork for Future Mining: Infrastructure Support by Knight Piésold
September 2025
Challenges of Tailings Transport Pumping Systems in Negative Static Head Applications
September 2025
Hydraulic Evaluation of Tailings Transport Systems in Mountainous Terrain: Density Wave Analysis
September 2025
The Role of Rheology Tests in the Design and Operation of Long-Distance Slurry Transport Systems
August 2025
Safe Dams, Straight Talk: The Knight Piésold Difference
July 2025
Knight Piésold Zambia: Building a Future of Engineering Brilliance and Local Empowerment
July 2025
Water Engineering for Modern Mining: Bridging Mining with Sustainability
June 2025
The Essence of Material Compatibility in Advanced Barrier Systems of Existing TSFs
June 2025
Inverted Barriers in Tailings Storage Facilities: Lessons Learnt
June 2025
Prioritizing the Mitigation of Legacy Geomechanical Mine Hazards Using a Risk-Based Approach
May 2025
Knight Piésold: Sustainable Projects in DRC Through Baseline Studies
April 2025
Advancements in Geotechnical Investigations for the Characterisation of Upstream Tailings Dams in SA
November 2024
Knight Piésold: Commitment to African Excellence
November 2024
Design of a Co-disposal Facility for Thickened Tailings and Potentially Acid-generating Waste Rock
November 2024
Compaction Sensitivity in Tailings Stack Infiltration Modeling: Unsaturated Properties Uncertainty Analysis
November 2024
Volumes of Dam Material Mobilized by Erosion During Tailings Dam Failure Events
October 2024
Estudio de rotura de una presa de jales en la zona centro-norte de México
September 2024
Grouting to Reduce Seepage at Neckartal Dam, Namibia
September 2024
Influence of Pre-Existing Mobilized Zones on B3 Cave Propagation and Initial Subsidence at the New Afton Mine
September 2024
Importance of Indigenous Community Engagement related to ARD/ML and Long-Term Water Quality