Steel Reticulation Design Excels

Steel Reticulation Design Excels

Publication: IMIESA
Issue: November/December 2018

Serving the growing needs of the City of eThekwini’s industrial and residential sectors is an expanding network of steel pipelines that traverse the hilly terrain common in this region. The challenging topography calls for innovative design and construction methodologies, which had a direct bearing on the pipeline reticulation system adopted.

For the Western Aqueduct Phase 2 component from Inchanga to Hillcrest, the steel pipes selected were manufactured and supplied by Hall Longmore, a market leader in South Africa and internationally since 1924. Both contracts for Phase 2 were completed in 2015.

Contract WS6190 comprised some 7 km of DN 1 600 steel pipe from Inchanga Station to Alverstone Nek Reservoir, with a short section of DN 1 400 steel pipe at Alverstone Nek Reservoir. The maximum static pressure in this stage is 29 bar, requiring 13.5 mm thick X65-grade steel pipe.

The final section (Contract WS6191) comprised approximately 7.5 km of DN 1 400 steel pipe from Alverstone Nek Reservoir to the Ashley Drive Break Pressure Tank (BPT). The maximum static pressure in this case is 25 bar, requiring 12 mm thick X65-grade steel pipe at high-pressure sections. The Ashley Drive BPT was designed for a through-flow capacity of 400 M?/day.

The Western Aqueduct was conceived as a large-diameter, thin-walled, continuously welded steel pipe. The steel pipe was selected to be both economical and functional. In low-pressure areas, this typically meant using the thinnest available X42-grade steel pipe, subject to typical slenderness limits not being exceeded. The thinnest wall was 10 mm on the DN 1 400 pipeline and 12 mm on the DN 1 600 pipeline, giving respective slenderness ratios of 140 and 133.

When pressure increases necessitated higher-strength pipe, the grade of steel pipe was changed in the first instance before increasing the wall thickness, as this was found to be a more economical solution – e.g. 10 mm wall thickness X42-grade pipe was upgraded to 10 mm thick X52-grade pipe, rather than, say, 12 mm thick X42-grade pipe. The highest grade of pipe specified was a 13.5 mm thick X65-grade steel pipe with a minimum yield strength of 448 MPa.

The pipeline was designed to be continuously welded, which resulted in the pipe wall stresses having to be calculated at every point of intersection. Because concrete thrust blocks were not a practical means of restraining longitudinal forces in such a large-diameter pressurised pipeline, these forces were taken up in the pipe itself.

 

Download the full technical paper.

Download

Recent Insights

May 2023
Is the Implementation of Dry Stacking for Tailings Storage Increasing? A Southern African Perspective
February 2023
Canadian Consulting Engineer's Lifetime Achievement Awards: Jeremy Haile
February 2023
Geotechnical Characterization of Collapsible Salty Sands Subjected to Monotonic and Cyclic Loadings – A Case Study for Areas with High Seismicity
November 2022
Application of the 3D Limit Equilibrium Method in Tailings Dam Breach Analysis
November 2022
Evaluation of Tailings Behaviour for Dam Breach Assessments
November 2022
Tailings Improvement by Stress-Densification from Waste Rock Capping
November 2022
Transforming Tailings Management Systems toward Alignment with the GISTM: A Case History
October 2022
Managing Excessive Pit Wall Deformation of Weak Rock Mass
October 2022
State-of-the-art Method for Estimating Long-term Hydroclimatic Conditions for Tailing Dam Water Management and Dam Safety Planning
August 2022
Observed Subsidence Progression at New Afton Mine in Response to Lift 1 Mining
June 2022
Hydrometric Monitoring and Effluent Discharge Mixing in Challenging Natural Conditions
May 2022
Inundation Modelling of Non-Newtonian Tailings Dam Breach Outflows
May 2022
Video: Tailings Management Compliancy Picks Up Momentum
May 2022
A Catch up with...Richard Elmer
February 2022
Engineer of Record Services for Tailings Facilities
November 2021
Knight Piésold's Projects Commended at Prestigious Awards
November 2021
Advances in Ensuring Tailings Dam Safety
November 2021
Gearing Up for Growth in Zambia
October 2021
Climate Change Effects on Rainfall Extremes and Implications for Highway Drainage Structures
October 2021
Knight Piésold, aliado de la minería sustentable