Design of the Box Canyon Scheme

Design of the Box Canyon Scheme

Publication: International Journal on Hydropower & Dams
Issue: Issue Four, August 2017

The 16 MW Box Canyon hydroelectric project ranks among the most hydraulically complex of any run-of-river hydro project in North America, if not the world. The project, which is located in the McNab Creek watershed, 40 km northwest of Vancouver, British Columbia, has nine intake structures on different creeks and tributaries. All nine feed into a single, high-pressure penstock that directs water to the powerhouse containing a single six-jet vertical axis Pelton generating unit.

The owner, Box Canyon Hydro Corp (a subsidiary of Elemental Energy Inc.) retained Knight Piésold Ltd to assist with:

  • concept development, optimization, environmental assessment, and permitting;
  • detailed design; and,
  • operational monitoring of the facility.

Initial investigations began in 2004, at which time the project concept was a 7 MW facility with a single intake on Box Canyon creek. Through optimization studies, which included site investigations and detailed hydrological studies, Knight Piésold revised the design to the current 16 MW arrangement. The design required addressing hydraulic, waterhammer and environmental flow release complexities, which are not typical for a single intake, run-of-river hydro project.

The project is within the traditional territory of the Squamish Nation, a valued partner on the project, and includes intake structures on three main tributaries to McNab Creek (Box Canyon, Marty, and Cascara Creeks) as well as six minor tributary diversions. Each intake is designed to meet unique water licence conditions that are intended to address the various hydrology, river morphology, and fish species distributions along the creeks and tributaries. The general arrangement and a schematic of the project are shown in Figs. 1 and 2. Key components of the project are highlighted in the photographs, and details for the major components of the project are summarized in the Table.

 

Download the full article.

Download

Recent Insights

May 2023
Is the Implementation of Dry Stacking for Tailings Storage Increasing? A Southern African Perspective
February 2023
Canadian Consulting Engineer's Lifetime Achievement Awards: Jeremy Haile
February 2023
Geotechnical Characterization of Collapsible Salty Sands Subjected to Monotonic and Cyclic Loadings – A Case Study for Areas with High Seismicity
November 2022
Application of the 3D Limit Equilibrium Method in Tailings Dam Breach Analysis
November 2022
Evaluation of Tailings Behaviour for Dam Breach Assessments
November 2022
Tailings Improvement by Stress-Densification from Waste Rock Capping
November 2022
Transforming Tailings Management Systems toward Alignment with the GISTM: A Case History
October 2022
Managing Excessive Pit Wall Deformation of Weak Rock Mass
October 2022
State-of-the-art Method for Estimating Long-term Hydroclimatic Conditions for Tailing Dam Water Management and Dam Safety Planning
August 2022
Observed Subsidence Progression at New Afton Mine in Response to Lift 1 Mining
June 2022
Hydrometric Monitoring and Effluent Discharge Mixing in Challenging Natural Conditions
May 2022
Inundation Modelling of Non-Newtonian Tailings Dam Breach Outflows
May 2022
Video: Tailings Management Compliancy Picks Up Momentum
May 2022
A Catch up with...Richard Elmer
February 2022
Engineer of Record Services for Tailings Facilities
November 2021
Knight Piésold's Projects Commended at Prestigious Awards
November 2021
Advances in Ensuring Tailings Dam Safety
November 2021
Gearing Up for Growth in Zambia
October 2021
Climate Change Effects on Rainfall Extremes and Implications for Highway Drainage Structures
October 2021
Knight Piésold, aliado de la minería sustentable