Landslide Risk Management for the Construction and Operation of the Upper Lillooet River Hydroelectric Facility Near Pemberton, BC

Landslide Risk Management for the Construction and Operation of the Upper Lillooet River Hydroelectric Facility Near Pemberton, BC

Author: James Haley, Pierre Friele
Conference: Geohazards 7
Date: June 3-6, 2018

ABSTRACT
The Upper Lillooet River Hydroelectric Facility is situated approximately 60 km northwest of Pemberton in southwest British Columbia, Canada. The site is located on the north side of the Mount Meager Volcanic Complex (MMVC), which comprises weak, locally hydrothermally altered rocks and is especially prone to large (>1 Mm3) landslides.

Landslide risk management plans were developed for both the construction and operational phases of the project. Under the framework of the landslide risk management plans, the work areas at the site were assigned one of three hazard ratings (Low, Moderate or High). The ratings reflect the return-frequency and magnitude of landside that would be anticipated to affect the work area. A risk analysis was completed taking account of the predicted workforce requirements for each work area and the vulnerability of individuals to the hazards. The landslide hazard from the MMVC is seasonal and conditioned by weather. Four hazard alert levels were defined based on rainfall and temperature criteria. Risk mitigation requirements for each work area were determined with respect to the different hazard alert levels. In moderate and high risk areas, the key mitigation measures implemented at elevated alert levels were the use of a ‘spotter’, restricting access and temporarily implementing ‘Shutdown’ of work. Rainfall and temperature were continually monitored during construction using an on-site climate station, and the mitigation measures were varied accordingly.

The landslide risk was exacerbated when, in the summer of 2015, the area was affected by a wildfire. Rock fall and boulder fall hazards were mitigated by undertaking scaling work and constructing a protection berm, and enhanced ‘Shutdown’ procedures were implemented. The management plan for the operational phase of the project incorporates a full Quantitative Risk Assessment for each work area and work activity with respect to Personal Individual Risk. The risk was evaluated against a threshold risk tolerance criteria of 1:10,000 per annum to verify the mitigation requirements.

 

Download the full technical paper.

Download

Recent Insights

October 2024
Estudio de rotura de una presa de jales en la zona centro-norte de México
September 2024
Influence of Pre-Existing Mobilized Zones on B3 Cave Propagation and Initial Subsidence at the New Afton Mine
September 2024
Importance of Indigenous Community Engagement related to ARD/ML and Long-Term Water Quality
September 2024
Effective Assessment of ARD/ML Potential for Non-Mining Infrastructure Projects
August 2024
CESA Aon Engineering Excellence Awards 2024: Kikagati Hydropower Plant
July 2024
Interview: Mario Lazo Emparanza, Regional Manager, Knight Piésold Chile
July 2024
Visionary Leadership: Driving Engineering Excellence in Africa with Vishal Haripersad
June 2024
Concept Feasibility and Predicted Behavior of Mining a Rock Tower with Drill-and-Blast Undermining Using Dynamic Three-Dimensional Discontinuum Numerical Models
June 2024
Estimating Shear Stress within a Clay Foundation Using the Burgers-Creep Model
June 2024
Laboratory Study of Manganese Mining Overburden Mixed with Lime as a Paving Subbase Layer
May 2024
Knight Piésold: Ensuring African Excellence in the DRC
May 2024
Wild Coast N2 Highway Project Taking Shape
May 2024
Interview: Guillermo Barreda, Gerente General, Knight Piésold Perú
April 2024
Risk Mitigation through Design Optimization Utilizing Seasonal Effects under Arctic Conditions at the Amaruq Mine
April 2024
Synthetic Rock Mass Modeling of Progressive Unravelling and Overall Slope Stability Using the Discrete Element Method
April 2024
Operational Slope Stability Risk Management for Large Open Pits at the Mount Milligan Mine – A Case Study
April 2024
Risk and Informed Approach to TSF Design and Operation
February 2024
Empowerment and Resilience
January 2024
Balancing Act: Water Usage Management Vital for a Sustainable Future
January 2024
A Difficult Balance Between Engineering, Environmental, Social and Economic Aspects